Authorization Object: K_ORDER

CO-OPA: General Authorization Object For Internal Orders

Category: Overhead Cost Orders

 

Definition

You can use this authorization object to issue access for the following
actions while working with internal orders:
Maintenance of order master data
Manual order planning
Budgeting of orders
Actions in the information system
You can issue authorizations for an area of responsibility in Overhead
Cost Controlling (CO-OM area of responsibility). If there is a cost
center responsible for the order, the CO-OM area of responsibility can
include the order, the responsible cost center, or a node in the
standard hierarchy of the Cost Center Accounting. If there is no
responsible cost center, the CO-OM area of responsibility applies only
to the order.

Click on the objects below, to expand data.

Object Fields

The list below includes the object’s fields, ordered by industry-standard importance:

AUFART Order Type Filled in 75% of cases
AUTHPHASE Internal Order Authorization: Authorization Phase Filled in 43% of cases
CO_ACTION Actions For CO-OM Authorization Check Filled in 93% of cases
KSTAR Cost Element Filled in 77% of cases
RESPAREA CO-OM Responsibility Area Filled in 78% of cases

 

Popularity Statistics

Average popularity of K_ORDER in roles: 2% (What does this mean?)
Average popularity of K_ORDER by users: 31% (What does this mean?)

Object K_ORDER is frequently used by users in the following areas:
FI:Financial Accounting
BC:Basis Components

Object K_ORDER is frequently used in the following business processes:
Internal Order Budget

Environmental Analysis

1. Common authorization objects used with K_ORDER:

A_IMA_ART Request Type For Appropriation Requests Objects appear together in 97% of cases
A_IMA_BUK Company Codes For Appropriation Requests Objects appear together in 97% of cases
A_IMA_GSB Business Areas For Appropriation Requests Objects appear together in 97% of cases
A_IMA_KOK Controlling Areas For Appropriation Requests Objects appear together in 97% of cases
A_IMA_MSTA User Status Of Appropriation Requests Objects appear together in 97% of cases
A_IMA_REQU Requesting Area Of Responsibility For Approp. Requests Objects appear together in 97% of cases
A_IMA_RESP Responsible Area Of Responsibility For Approp. Requests Objects appear together in 97% of cases
A_IMA_VSTA User Status For Appropriation Request Variants Objects appear together in 97% of cases
A_IMPR_APS Approval Level For Versions (Program Planning) Objects appear together in 97% of cases
A_IMPR_PRC Profit Center For Investment Program Positions Objects appear together in 97% of cases
A_IMPR_VER Persons Resp. For Investment Program Positions Objects appear together in 97% of cases
K_SUM_ORD CO-PC: Summarization – Orders Objects appear together in 97% of cases
A_IMPR_BUK Company Codes For Investment Program Positions Objects appear together in 96% of cases
A_IMPR_GSB Business Areas For Investment Program Positions Objects appear together in 96% of cases
A_IMPR_KOK Controlling Areas For Investment Program Positions Objects appear together in 96% of cases
A_IMTP_ART Program Type For Investment Programs Objects appear together in 96% of cases
C_AFKO_ACT Activities On Network Header Level Objects appear together in 96% of cases
C_ROUT Authorizations For Routings Objects appear together in 96% of cases
K_CKBS CO-PC: Base Planning Objects Objects appear together in 95% of cases
B_USERST_T Status Management: Set/Delete User Status Using Process Objects appear together in 94% of cases
C_PROJ_KOK PS: Controlling Area For Project Definition Objects appear together in 94% of cases
C_PROJ_PRC PS: Profit Center For Project Definition Objects appear together in 94% of cases
C_PROJ_VNR PS: Project Manager For Project Definition Objects appear together in 94% of cases
M_MATE_ZST Material Master: Change Status Of Batches Objects appear together in 94% of cases
Q_STCK_CHG Change Stock Posting Fields In UD Transactions Objects appear together in 94% of cases
C_PRPS_ART PS: Project Type Authorization For WBS Elements Objects appear together in 93% of cases
C_PRPS_KOK PS: Controlling Area Authorization For WBS Elements Objects appear together in 93% of cases
C_PRPS_KST PS: Cost Center Authorization For WBS Elements Objects appear together in 93% of cases
C_PRPS_PRC PS: Profit Center Authorization For WBS Elements Objects appear together in 93% of cases
C_PRPS_VNR PS: Project Manager Authorization For WBS Elements Objects appear together in 93% of cases
Q_UD_CODE Using Usage Decision Codes Objects appear together in 93% of cases
M_MATE_CHG Material Master: Batches/Trading Units Objects appear together in 92% of cases
C_PROJ_TCD PS: Transaction-Specific Authorizations In Project System Objects appear together in 91% of cases
Q_GP_CODE Use Of Group Codes Objects appear together in 91% of cases
Q_INSP_FIN Inspection Completion With Open Char./Insp.Pts Req. Conf. Objects appear together in 91% of cases
Q_INSPTYPE Inspection Type For The Insp. Lot Objects appear together in 91% of cases
I_TCODE PM: Transaction Code Objects appear together in 90% of cases
Q_MATERIAL Material Authorization Objects appear together in 90% of cases
Q_TCODE QM Transaction Authorization Objects appear together in 89% of cases
S_DATASET Authorization For File Access Objects appear together in 88% of cases
B_USERSTAT Status Management: Set/Delete User Status Objects appear together in 85% of cases
C_DRAD_OBJ Create/Change/Display/Delete Object Link Objects appear together in 84% of cases
C_TCLS_BER Authorization For Org. Areas In Classification System Objects appear together in 84% of cases
C_TCLS_MNT Authorization For Characteristics Of Org. Area Objects appear together in 84% of cases
K_CKPH CO-PC: Cost Objects Objects appear together in 84% of cases
K_ABC CO-ABC: General Authorization Object, Business Processes Objects appear together in 82% of cases
K_CSKS_PLA CO-CCA: Cost Center Planning Objects appear together in 81% of cases
K_CSKB_PLA CO-CCA: Cost Element Planning Objects appear together in 79% of cases
C_TCLA_BKA Authorization For Class Types Objects appear together in 78% of cases
K_TKA50 CO: Planner Profiles Objects appear together in 78% of cases
K_KA09_KVS CO: Version Objects appear together in 77% of cases
S_RFC Authorization Check For RFC Access Objects appear together in 69% of cases
K_AUFK_SET CO-OPA: Order Groups Objects appear together in 50% of cases
G_800_GRP Report Writer: Report Objects appear together in 49% of cases
G_803J_GJB Report Writer: Report Group Objects appear together in 48% of cases
G_800S_GSE Special Purpose Ledger Sets: Set Objects appear together in 45% of cases
K_REPO_OPA CO-OPA: Reporting On Orders Objects appear together in 44% of cases
K_CSKS_SET CO-CCA: Cost Center Groups Objects appear together in 41% of cases
S_ARCHIVE Archiving Objects appear together in 41% of cases
S_SCD0 Change Documents Objects appear together in 40% of cases
K_AUFK_ART CO-OPA: Order Types Objects appear together in 39% of cases
K_TP_VALU Transfer Price Valuations Objects appear together in 36% of cases
K_REPO_CCA CO-CCA: Reporting On Cost Centers / Cost Elements Objects appear together in 35% of cases
K_CCA CO-CCA: Gen. Authorization Object For Cost Center Accounting Objects appear together in 33% of cases
K_VRGNG CO: Bus. Trans., Actual Postings And Plan/Act. Allocations Objects appear together in 32% of cases
S_ALV_LAYO ALV Standard Layout Objects appear together in 18% of cases

  2. Appearance of K_ORDER in T-Codes:

CJ9B Copy WBS Plan to Plan (Collective) Used in 100% of cases
CJ9BS Copy WBS Plan to Plan (Indiv.) Used in 100% of cases
CJ9C Copy WBS Actual to Plan (Collective) Used in 100% of cases
CJ9CS Copy WBS Actual to Plan (Indiv.) Used in 100% of cases
CJ9FS Copy Project Costing (Indiv.) Used in 100% of cases
IM40 Change supplement on operative objs Used in 100% of cases
IM42 Change budget operative objects Used in 100% of cases
IM48 Change return on operative objects Used in 100% of cases
IMA2 Change appropriation request Used in 100% of cases
IMA2N Change Appropriation Request Used in 100% of cases
KO14_OLD Copy Order Plan Version (old) Used in 100% of cases
KOB6 Order: Act. amt. line item settlmt. Used in 100% of cases
KOB7 Line item sel. inv.meas. for retmt. Used in 100% of cases
KOCM Conversion Classification: AUFK Used in 100% of cases
KOM1 Create CO model order Used in 100% of cases
KOM3 Display CO model order Used in 100% of cases
KOPU Execute Orders for Plan Revaluation Used in 100% of cases
KOWEB_CREATE_OR Create Order Master Data (Web) Used in 100% of cases
KOWEB_EDIT_OR Edit Order Master Data (Web) Used in 100% of cases
KPA6 Change Primary Cost Element Planning Used in 100% of cases
KPA7 Display Primary Cost Elem. Planning Used in 100% of cases
QA02A Change Inspection Lot Used in 100% of cases
IMA11 Individual Processing Used in 99% of cases
IMA12 Individual Processing (Planner) Used in 99% of cases
KKF1 Create CO Production Order Used in 99% of cases
KKF4 Change CO-FA Plan Values Used in 99% of cases
KKF5 Display CO-FA Plan Values Used in 99% of cases
KO08 Data Transfer for Order Master Data Used in 99% of cases
KO14 Copy Planing for Internal Orders Used in 99% of cases
KO24 Change Order Supplement Used in 99% of cases
KO25 Display Order Supplement Used in 99% of cases
KO26 Change Order Return Used in 99% of cases
KO27 Display Order Return Used in 99% of cases
KOC2 Run Selected Reports Used in 99% of cases
KOK6 Collect. Printing of Internal Orders Used in 99% of cases
KOM2 Change CO Model Order Used in 99% of cases
KPD6 Change Stat. Key Figure Plan Data Used in 99% of cases
KPD7 Display Stat. Key Figure Plan Data Used in 99% of cases
KPHR Transfer HR Costs to CO Used in 99% of cases
KRMI Run Sched. Header: Line Items Actual Used in 99% of cases
KKF2 Change CO Production Order Used in 98% of cases
KO13 Display Order Plan (Overall, Year) Used in 98% of cases
KPF7 Display CElem./Acty Input Planning Used in 98% of cases
QK05 Confirmed activities for insp. lot Used in 98% of cases
KKF3 Display CO Production Order Used in 97% of cases
KO12 Change Order Plan (Overall, Year) Used in 97% of cases
KO22 Change Order Budget Used in 97% of cases
KOB3 Orders: Line Items Variance Used in 97% of cases
KOB5 Orders- Maint. line item settlement Used in 97% of cases
KPF6 Change CElem/Activity Input Planning Used in 97% of cases
QA12 Change usage decision with history Used in 97% of cases
QA14 Change UD without history Used in 97% of cases
KABP Controlling Documents: Plan Used in 96% of cases
KOB4 Orders: Budget Line Items Used in 96% of cases
KOB8 Orders: Line Items WIP/Results Anal. Used in 96% of cases
KOBP Orders: Plan line items Used in 96% of cases
KOC4 Cost Analysis Used in 96% of cases
QA02 Change Inspection Lot Used in 96% of cases
QA11 Record usage decision Used in 96% of cases
KO23 Display Order Budget Used in 95% of cases
KOB2 Orders: Commitment Line Items Used in 95% of cases
QA13 Display usage decision Used in 95% of cases
KABL Order: Planning Overview Used in 94% of cases
QA03 Display inspection lot Used in 93% of cases
KSB5 Controlling Documents: Actual Used in 85% of cases
KOK2 Collective Proc. Internal Orders Used in 78% of cases
KOK4 Aut. Collect. Proc. Internal Orders Used in 78% of cases
KO04 Order Manager Used in 76% of cases
KOK3 Collective Disp. Internal Orders Used in 75% of cases
KO01 Create Internal Order Used in 74% of cases
KO02 Change Order Used in 72% of cases
KOK5 Master Data List Internal Orders Used in 72% of cases
KO03 Display Internal Order Used in 70% of cases
KOB1 Orders: Actual Line Items Used in 63% of cases